TM 10-7310-282-10
0015 00
NOTE
When installing a new oven section without base on a previously installed oven section or
sections, the top should be removed and the new deck installed as in Steps 4 through 7. The
main top should then be reinstalled, making sure that the vent stack engages with the vent
cover and that the two long screws are replaced halfway along the main top sides.
4
1
2
3
Preparation for Use
1. Before first use, clean oven decks with a soft brush.
2. To release any paint fumes or moisture content, set the thermostat at 300F and the toggle switches
to ON or MEDIUM, as applicable.
3. Allow ovens to operate for 6 to 8 hours with the damper wide open.
0015 00-3